Print this page

Aluminium smelter electricity battle gets backing

  • font size decrease font size decrease font size increase font size increase font size

Southland community and business leaders are backing the local aluminium smelter in its battle to pay lower electricity transmission costs. It costs $918 million to run New Zealand's 12,000km national grid, and the smelter has to pay $60.8m a year of that cost.

It originally hoped to reduce that to about $10m, because it only uses one 160km power line, from Manapouri to Tiwai Point, and argued it should not have to pay for wires over 1000km away in Northland or Auckland.

But the Electricity Authority's series of reform proposals is progressively dashing those hopes.

Its latest, and probably penultimate, proposal lowers the smelter's bill only slightly, from $60.8m to $47.4m or $41.9m, depending on how it is assessed.Tim Shadbolt

Invercargill mayor Tim Shadbolt said that was not nearly good enough.

"We are going to fight it all the way, and we have been getting quite good at fighting these sorts of battles," Mr Shadbolt said.

"I believe it is a case of rallying the troops and getting the South Island mayors together and trying to explain to people what our case is and hoping they will take the side of justice."

Continue to full article  |  Dec 19, 2016  |